This page provides links to Outage Plans for the Long Range Significant Outages and 45-Day Outage Planning Processes. To receive updates when outage plans are posted or revised, sign up for the CAPACITY_L e-mail forum.
Schedule for NWPP 45-Day Outage Coordination Process - updated 01MAR10
Immediate to Near Term Changes to Outage Plans
45-Day Outage Plan
The following estimates are for information purposes only and are subject to change as studies are done to confirm limits.
September 2010
Revised Coordinated Outage Plan with Capacity Estimates for September 2010 - Posted 29JUL10
Coordinated Outage Plan with Capacity Estimates for September 2010 - Posted 28JUL10
Initial Outage Plan with Capacity Estimates for September 2010 - Posted 20JUL10
August 2010
Final Outage Plan with Capacity Estimates for August 2010 - Posted 01JUL10
Coordinated Outage Plan with Capacity Estimates for August 2010 - Posted 23JUN10
Initial Outage Plan with Capacity Estimates for August 2010 - Posted 17JUN10
July 2010
Revised Final Outage Plan with Capacity Estimates for July 2010 - Posted 03JUN10
Final Outage Plan with Capacity Estimates for July 2010 - Posted 02JUN10
Coordinated Outage Plan with Capacity Estimates for July 2010 - Posted 27MAY10
Revised Initial Outage Plan with Capacity Estimates for July 2010 - Posted 18MAY10
Initial Outage Plan with Capacity Estimates for July 2010 - Posted 17MAY10
Long Range Significant Outages
The following outages for October-December 2010, are for information purposes only. Outages are still being adjusted and/or moved.
There are no path capacities provided. Estimates of path capacities will be given as we go into the "45-day" process. These outages are subject to change.
OCTOBER 2010 - Posted 20JUL10
NOVEMBER 2010 - Posted 20JUL10